Technical Barriers to Decarbonization

Large commercial and residential buildings must overcome various hurdles before implementing deep retrofits or capital projects that help achieve building decarbonization. In this section, we address technical barriers and questions often faced by building owners and retrofit project developers. 

Decentralized Systems and Tenant Equipment

Decentralized Systems and Tenant Equipment


Access to Occupied Spaces.

Lease Concerns.

Regulatory Limitations - Rent Stabilized Apartments

  1. The building owner is required to provide free heat and hot water.
  2. No mechanism to recover investment in new systems is necessary to achieve decarbonization.
  3. Buildings are capital constrained

Split Incentives (tenants pay for energy).

Infrastructure

Infrastructure


Con Edison Steam: assume district steam system will decarbonize

High temperature renewable resources are limited and face hurdles:

  • Deep Bore Geothermal
  • Renewable Hydrogen
  • Carbon Capture and Sequestration
  • Biomethane
  • Electric Boilers
  • High-temperature thermal storage
  • Hight-temperature industrial heat pumps
  • Waste Heat Capture and Reuse
  • Fission


Facade and Windows

Facade and Windows


Work must be completed at the end of facade/window useful life; very long useful life

Building code

Glazing reduction at odds with aesthetic/marketability concerns

Difficult installing with occupied spaces

Reduce Local Law 11 recurring cost via overcladding

  • Aesthetic concerns
  • At odds with historic preservation
  • Capital intensive
  • Lot line limitations

Technology Limitations

  • Need higher R-value/inch for thinner wall assembly:

    • Vacuum insulated panels

    • Aerogel panels/batts

    • Zero-GWP blowing agents for closed cell spray foam (nitrogen blowing agent needs to be more widely adopted)



Ventilation

Ventilation


Energy Recovery Ventilation (ERV)

  • Space constraints
  • System tie-in point accessibility/feasibility

Rooftop Supply Air (Reznor) Unit Alternatives

  • Heat pump alternatives to eliminate resistance heat
  • Combine with ERV

HVAC Load Reduction (HLR) Technology

  • Vent or capture exhaust gases
  • Space constraints
  • System tie-in point accessibility/feasibility

Central vs. Decentralized Ventilation Systems

Direct Outside Air System (DOAS)

  • Modular perimeter ducted air heat pumps: 

    • Competition for leasable space
    • Space constraints

Ventilation Points-of-Entry

  • Aesthetic concerns
  • Lot line facades/building setbacks
  • Competition with leasable space
  • Space constraints


Heat Pump Limitations

Heat Pump Limitations


Variable Refrigerant Flow (VRF)

  • Fire and life safety concerns about volume of refrigerant gas located within occupied spaces.

Regulatory risk from new refrigerant policies

PTAC and VTAC

Ducted Supply/Exhaust Air Source Heat Pumps

Domestic Hot Water

  • Central DHW Systems: 

    • Limited domestic production
    • Performance not confirmed by independent third parties

    • More demonstration projects needed
  • Decentralized DHW Systems

More open-source interconnection between devices/interoperability is needed to achieve energy distribution flexibility and capacity expansion:

  • Air source that has a manifold connection to interconnect with water source or refrigerant gas distribution
  • Interconnectivity/simplified heat exchange between refrigerants/water/air, etc.
  • Other options and add-ons



Crossover Device or "Magic Box" Technology

Crossover Device or “Magic Box” Technology


Multi-purpose technology for heating, cooling, heat exchange and ventilation, filtration, and/or domestic hot water

Domestic production and supply chain is limited

Small players operating in this space

Technology is not tested over long operational periods

  • Daikin, Nilan, Zehnder, Drexel und Weiss, Minotair, Build Equinox, Clivet


Zero Carbon Fuel Limitations

Zero Carbon Fuel Limitations


Green Hydrogen

Renewable Natural Gas


Low-Carbon Fuels

Low-Carbon Fuels


Biofuel

Biomethane


Renewable Energy Procurement Limitation

Renewable Energy Procurement Limitations


REC Purchasing

  • NYSERDA monopolizes REC purchasing from renewable energy projects


Pending Carbon Trading Program Limitations